Taco Bell/KFC

Category:

Date: 11/1/2012

Duration: 3 Days

New construction for new restaurant.

Project Summary:

  • Helical Pile Type: square shaft 1.75
  • # of Helical Piles: 72
  • Location: Philadelphia, PA
  • Installation Depth: 25 ft
  • Equipment Used: Mid-Sized Excavator and 12,000 foot pound drive head
  • Challenge/Unique Aspect: Helicals were used in lieu of driven piles due to close proximity of neighboring buildings, all vibratory concerns were dismissed due to helicals.
  • Engineer/Architect: GDP Associates and PSI Engineering and Consulting
  • General Contractor: YUM Brands