Interstate Storage and Pipeline Bridge Project

Interstate Storage & Pipeline, a major jet fuel supplier, had to create an alternate route to their pump house. THE CASTLE GROUP was retained to design and construct a pre-fabricated bridge. The use of  Helical Piles was an integral part of the design.

Project Summary:

  • Helical Pile Type: 1.75” Square Shaft
  • # of Helical Piles: 5
  • Location: New Jersey
  • Installation Depth: 35’
  • Equipment Used: Mini Excavator, 12K Drive head
  • Challenge/Unique Aspect: Road closures and site stoppages were prevented due to small and fast mobilizations of material and equipment.
  • Engineer/Architect: W.J. Castle, P.E. & Associates, P.C.
  • General Contractor: Hydro-Marine Construction Co., Inc.