Production install for LINAC – helical pile foundation holding the concrete slab that the LINAC rests on.

Project Summary:

  • Helical Pile Type: 2″ Square Shaft
  • # of Helical Piles: 28
  • Location: Cherry Hill, NJ
  • Installation Depth: 90′ – 107′
  • Equipment Used: 30,000 foot pound drive head, caterpillar 315, digital torque indicator
  • Challenge/Unique Aspect: exposed footing of the building
  • General Contractor: D’Angelo Brothers